SITE WORK
Meet customer at Homesite ***
Clearing
Locate Utilities
Temporary Power/ Meter
Stake out House
Sewer Connections **
Foundation Excavate**
Septic System**
Well Water**
CONSTRUCTION BEGINS
Footers/Foundation Work**
Brick Ledges
Footer Drains
Downspout Drains**
Insulation on Exterior of Walls or Slab areas**
Backfill/Rough Grade Gravel fill per Code**
Plumbing Drain Stacks**
HVAC for Slab**
Concrete Floor
Set Beams
FRAMING BEGINS - ROUGH
Rough framing
Install Windows and Doors
Roofing
Install Fireplace
Meet customer at Home ***
Exterior Siding/Brick/Stone
Plumbing
HVAC
Electrical
Rough Inspections**
Prewire Security/ Speakers/ Vacuum/ Intercom/Computer
Insulate/Caulk**
Drywall
EXTERIOR FINISH
Exterior Concrete**
Final Grade**
Check Doors / Windows and Screens
Paint exterior Doors & Trim
Caulking completed
FINISH WORK BEGINS
Pre-paint
Finish Trim / Cabinets / Fireplace
Paint
Install Hard Flooring
Countertops
HVAC Finish / Plumbing Finish / Electrical Finish
Specialties Finish Security / Speakers / Vacuum Intercom/Computer
Install Light Fixtures
Install Carpet
Install Hardware
Final Clean
Punch-Out Items
Final Inspections**
Meet customer at Home ***
Closing